* How to total a day's planned effort?
@ 2008-04-13 11:59 Manish
0 siblings, 0 replies; only message in thread
From: Manish @ 2008-04-13 11:59 UTC (permalink / raw)
To: org-mode
Hello all,
While doing the weekly review, I schedule things based on various
days. I use column view to see estimated effort for various scheduled
tasks in a weekly view. Then I do a mental sum of the effort
scheduled for the day and I find I am over-committing myself and have
to reschedule some TODOs to reduce that day's load. I was wondering
if it's somehow possible to show the sum of estimated effort as part
of the overlay under the estimate column on the same line (or any
other suitable place) that shows the date. Like so:
,----
| Task | Estimated | Actual |
| Sunday 13 April 2008
| Category: Sched. 2x: Test task | 2:00 | |
| Monday 14 April 2008 W16 | 14:00 | |
| Something: Write the report | 6:00 | |
| Oracle: Tune the beast | 8:00 | |
`----
How do others take care of this?
-- Manish
^ permalink raw reply [flat|nested] only message in thread
only message in thread, other threads:[~2008-04-13 11:59 UTC | newest]
Thread overview: (only message) (download: mbox.gz follow: Atom feed
-- links below jump to the message on this page --
2008-04-13 11:59 How to total a day's planned effort? Manish
Code repositories for project(s) associated with this public inbox
https://git.savannah.gnu.org/cgit/emacs/org-mode.git
This is a public inbox, see mirroring instructions
for how to clone and mirror all data and code used for this inbox;
as well as URLs for read-only IMAP folder(s) and NNTP newsgroup(s).