Thank you,
I've changed to
#+PROPERTY: Effort_ALL 2d 1w 2w 3w 4w 2m
#+COLUMNS: %40ITEM(Task) %17Effort(Estimated Effort){:} %CLOCKSUM
but there is no mapping between days, weeks, months and hours. For example,
'2d' + '1w' is summed as '3:00'. How can I change this?
The best for me would be to have the summed effort in weeks.
Best regards,
Johan
> But I'd like to make estimates in days, weeks or even months.You can certainly do that. Have a look at org-effort-durations. You
could for example define the effort as '2d', '4w' or '7m'.
You might be able to do something along this line. Have a look at the
> And have spent time displayed in percentage of the estimate. Is this
> possible?
doc string of org-properties-postprocess-alist where it gives you an
example on how to calculate the remaining time (clocked vs estimated).
HTH
--
Christian Egli