Hi Eric,

Thank you, I will have a closer look at org-depend, although it seems to me that it's more 'depend' in the sense of 'this task has to be done for this other task to be doable'. But I only had a glimpse on the code.

Regards,

FC


On Sat, Jun 14, 2014 at 10:19 AM, Eric Abrahamsen <eric@ericabrahamsen.net> wrote:
Fletcher Charest <fletcher.charest@gmail.com> writes:

> Dear all,
>
> I was wondering if there was a way to link the status of two tasks in
> an agenda file (or even across multiple agenda files). Sometimes, a
> single task (in my case, updating my CV) might be a useful step in
> two different projects. If the tasks is marked DONE in one project
> (in one subtree), I would like the other one to be marked DONE as
> well. Is it possible or even implemented?
>
> Cheers,
>
> FC

There's an org-depend package in the contrib directory that's supposed
to do this, but I haven't looked at it before... Vanilla Org only does
dependencies within the same subtree.

E