[-- Attachment #1: Type: text/plain, Size: 491 bytes --] Hi there, Does anybody knows how to setup org to schedule repeated task between a specified range of dates. For example, suppose I plan to work on a grant proposal between 10 am - 1 pm every other day from May 1 to June 1, how would I do this ? My current practice is specify the start date with a repeater (in this case +2d), and then delete task when the deadline has passed. It though it would be more efficient I could assign a date range rather than just the start date. Cheers, M [-- Attachment #2: Type: text/html, Size: 695 bytes --]
Hi Marvin,
Marvin Doyley <marvinpas@gmail.com> writes:
> Hi there,
>
> Does anybody knows how to setup org to schedule repeated task between
> a specified range of dates. For example, suppose I plan to work on a
> grant proposal between 10 am - 1 pm every other day from May 1 to
> June 1, how would I do this ? My current practice is specify the
> start date with a repeater (in this case +2d), and then delete task
> when the deadline has passed. It though it would be more efficient I
> could assign a date range rather than just the start date.
>
>
> Cheers,
> M
If I understand your situation correctly, you might take a look at
Habits. If you mark them done, they will be rescheduled to the next date
you specified. Roughly it should look like this:
* TODO Work on proposal
:SCHEDULED: <2013-05-01 Wed 22:00 .+2d>
:PROPERTIES:
:STYLE: habit
:END:
But your are probably better off looking at the part of the manual
regarding habits.
Regards,
Alex
org-habit is not what I am looking for. I would like to do something like * TODO write proposal Scheduled:<2013-04-30 Tue 13:00-15:00 >--<2013-06-02 Mon> +2d The idea is to repeat this task every other day from 2013-04-30 to 2013-06-02 (from 13:30 to 15:00) cheers M
Hi Marvin,
Marvin Doyley <m.doyley@rochester.edu> writes:
> org-habit is not what I am looking for.
>
> I would like to do something like
>
> * TODO write proposal
> Scheduled:<2013-04-30 Tue 13:00-15:00 >--<2013-06-02 Mon> +2d
>
> The idea is to repeat this task every other day from 2013-04-30 to 2013-06-02 (from 13:30 to 15:00)
>
> cheers
> M
Ok, then I think diary sexp should do the trick. Try the following:
** TODO 13:00-15:00 write proposal
<%%(and (org-block 2013 4 30 2013 6 2) (org-cyclic 2 2013 4 30))>
Regards,
Alex
Thanks, this is exactly what I was looking for
cheers
M
I will give it a try
cheers
M
On Apr 29, 2013, at 3:56 PM, Alexander Baier <lexi.baier@gmail.com> wrote:
> Hi Marvin,
>
> Marvin Doyley <m.doyley@rochester.edu> writes:
>> org-habit is not what I am looking for.
>>
>> I would like to do something like
>>
>> * TODO write proposal
>> Scheduled:<2013-04-30 Tue 13:00-15:00 >--<2013-06-02 Mon> +2d
>>
>> The idea is to repeat this task every other day from 2013-04-30 to 2013-06-02 (from 13:30 to 15:00)
>>
>> cheers
>> M
>
> Ok, then I think diary sexp should do the trick. Try the following:
>
> ** TODO 13:00-15:00 write proposal
> <%%(and (org-block 2013 4 30 2013 6 2) (org-cyclic 2 2013 4 30))>
>
>
> Regards,
> Alex